September 2001 |
|
9th |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
The loop has finally been constructed, it
stands around 75ft high. The bunny hop after the loop, shown in photos 1
and 3, should give some nice floating airtime. Work has started on the
cobra roll. |
|
|
15th |
|
 |
 |
 |
 |
|
The bottom half of the lift has now been
constructed, and the cobra roll is also going vertical.
Almost all the ride has now arrived, including the final track for the heartline
rolls. |
|
|
26th |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
The cobra roll and both
corkscrews are now complete. Riders will travel through the
corkscrews at a very high speed, with an intense approach
from underground. Final turnaround supports are also up,
photo 7. |
|
|
October
2001 |
|
3rd |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
The circuit is almost complete. Only the brake
run, station, and transfer track are remaining.
X:\ No Way Out's building has had a new corner support installed. It has been
modified due to Project Odyssey's transfer track requiring the space. Compare
photo 12 with this one.
|
|
|