July 2001 |
|
15th |
|
 |
 |
 |
 |
|
Photo 1 shows a new concrete access path
that has been constructed through the water. A large scaffolding structure
has been built on the area where the lift hill will go, it is at least
60ft high. |
|
|
21st |
|
 |
 |
 |
|
 |
 |
 |
|
Track and supports finally arrive! There are
currently just four pieces of track for the station and lift hill. Photo six
shows many supports, looking through the bridge. |
|
|
29th |
|
 |
 |
 |
|
 |
 |
 |
|
As more and more deliveries arrive each day,
the top half of the lift hill supports were erected this week. |
|
|
August 2001 |
|
3rd |
|
 |
 |
 |
|
The upper lift hill has now
been topped off with track. The bottom half and the station
will be done at a later date. The supports for the heartline
rolls have started to be placed. |
|
|
25th |
|
 |
 |
 |
 |
 |
|
 |
 |
 |
 |
 |
|
The turn around and drop are complete, and
more supports are being placed down all over the site. Work has begun on
the queue line, photo 6. Last two photos taken by John Wardley on
28/08/01. |
|
|