October 2002 |
|
13th |
|
 |
 |
 |
 |
 |
|
 |
 |
 |
 |
 |
|
Once again the track has gone up at a fast
rate, now complete up to the first helix. Station theming continues along
with the delivery of the first train. |
|
|
24th |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
The last piece of track was put in to place on the
18th October. Theming work continues on the station volcano, looks impressive
already. Note that red bricks have arrived for paving the area |
|
|
November 2002 |
|
2nd |
|
 |
 |
 |
 |
 |
|
Work continues on the station volcano; the
tunnel entrance and queue line area are now being covered. Red paving has
has been laid starting under the lift, which is nice to see instead of
tarmac. |
|
|
18th |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
The majority of the rides
electronics have been connected, testing starts at the
beginning of December. |
|
|