June 2003 |
|
9th |
|
 |
 |
 |
 |
|
Initial construction. Hoarding is put up around the site and a
temporary path has been created next to
Toadie's Crazy Cars for easier access to Beanoland and Mystic
East. Action Man has started to be dismantled. |
|
|
October 2003 |
|
31st |
|
 |
 |
 |
 |
 |
|
 |
 |
 |
 |
 |
|
The majority of the coaster foundations have
been laid, and initial steelwork has now arrived. Work is on target for
the opening on March 27th 2004. The last two photos were taken on
1/11/03. |
|
|
November 2003 |
|
24th |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
Since the last update, the lift hill,
helix, and block 3 section has been built.
They are not constructing the coaster in
ride order due to accessibility reasons. |
|
|
December 2003 |
|
8th |
|
 |
 |
 |
 |
 |
|
 |
 |
 |
 |
 |
|
Approximately half the
coaster is now complete. We look forward to the more intense first
half, constructed next. The last photo shows the structure of the
large play area building going up. |
|
|
19th |
|
 |
 |
 |
 |
|
 |
 |
 |
 |
|
With some of the larger sections of the ride now complete,
it is proven that Dragon's Fury will not be a tame coaster.
Track wise, only the drop, Immelmann turn and section after
is left to construct. |
|
|